Instead of Excel: enter land, units, build costs and timeline – Offmarketpool calculates costs, revenue, MaBV staged payments, monthly cash flow, equity and loan need, margin, IRR and the residual land value. Then manage the project with plan vs. actual and sales status.
Non-binding project calculation – no financing commitment, no legal or tax advice.
| Land | 800.000 € |
| Acquisition costs | 68.000 € |
| Site development | 0 € |
| Build costs | 2.880.000 € |
| External works | 0 € |
| Soft costs | 518.400 € |
| Contingency | 144.000 € |
| Sales | 148.500 € |
| Marketing | 0 € |
| Financing (interest) | 22.249 € |
| Total cost | 4.581.149 € |
| Instalment | Construction stages | % | due |
|---|---|---|---|
| 1 | Earthworks | 30 % | 2027-07 |
| 2 | Shell | 28 % | 2028-02 |
| 3 | Roof, Heating rough-in, Plumbing rough-in, Electrical rough-in | 11,9 % | 2028-04 |
| 4 | Windows, Interior plaster | 11,2 % | 2028-07 |
| 5 | Screed, Bathroom tiles | 4,9 % | 2028-10 |
| 6 | Ready for occupancy, Facade | 10,5 % | 2029-01 |
| 7 | Full completion | 3,5 % | 2029-04 |
Highest land price at a 15 % target margin on cost: 560.000 € (373 € per m² of land)
| Sale prices −5 % | 121.657 € | 2,7 % |
| Sale prices +5 % | 616.007 € | 13,5 % |
| Build costs +10 % | -3.064 € | -0,1 % |
| Build costs −10 % | 738.199 € | 17,5 % |
| Construction +6 months | 370.136 € | 8,1 % |
| Interest +2 points | 361.102 € | 7,9 % |